Build DesignSolutions Development

Development › Kingsford › Site #11

Standalone site

Address locked, Kingsford

1 house today → about 10 homes as apartments, up to 4 storeys. About 800 m², 18 m frontage, zone R3.

Residual land valueA$3.5m
Likely ask (1 house)A$2.8mFrom the 1 July 2025 land value x 1.15
HeadroomA$750k
Claim this site

A$182 inc GST · 3 months

A claim takes this site off the market for every other member for 3 months and opens its address, lot outline, exact figures and neighbours to you.

Sites whose best option clears a 40% margin on cost at the likely ask are A$387. One claim credit claims any site.

Card payment through Stripe. Have an account? Sign in. A claim is exclusive on Build Design Solutions only: it gives no right over the property, and the owner can still sell to anyone. How claims work.

Every option the rules allow

OptionHomesStoreysGFARealisationCostsResidual land valueHeadroomProfit at likely ask
Apartments, up to 4 storeysLow and Mid-Rise (400 to 800 m) · FSR 1.5:1 · 17.5 m 1041,250 m² A$16.0mA$8.0mA$3.5mA$750k A$2.5m22% on cost · 16% on revenue
Cost stack
  • Construction 1,250 m² at A$4,900/m²A$6.0m
  • Basement parkingA$400k
  • DemolitionA$45k
  • Consultants, DA and certification (9%)A$600k
  • Contributions (A$28,000 per new home)A$300k
  • Contingency (5%)A$350k
  • Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$2.8m instead leaves A$2.5m pre-tax on a total development cost of A$12.0m.
Apartments, up to 6 storeys + affordable housing bonusLow and Mid-Rise + Chapter 2 bonus (15% affordable) · FSR 1.95:1 · 22.8 m 1561,750 m² A$20.0mA$11.0mA$2.5m-A$250k A$3.0m19% on cost · 14% on revenue
Cost stack
  • Construction 1,750 m² at A$5,500/m²A$9.0m
  • Basement parkingA$550k
  • DemolitionA$45k
  • Consultants, DA and certification (9%)A$850k
  • Contributions (A$28,000 per new home)A$425k
  • Contingency (5%)A$500k
  • Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$2.8m instead leaves A$3.0m pre-tax on a total development cost of A$15.0m. Includes 15% affordable housing at 65% of market.
TownhousesLow and Mid-Rise · FSR 0.9:1 · 12 m 52800 m² A$9.0mA$3.8mA$2.4m-A$350k A$1.0m14% on cost · 11% on revenue
Cost stack
  • Construction 800 m² at A$4,100/m²A$3.0m
  • DemolitionA$45k
  • Consultants, DA and certification (9%)A$275k
  • Contributions (A$28,000 per new home)A$110k
  • Contingency (5%)A$170k
  • Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$2.8m instead leaves A$1.0m pre-tax on a total development cost of A$7.0m.
Dual occupancyLow and Mid-Rise · FSR 0.9:1 · 12 m 22500 m² A$5.5mA$2.3mA$1.7m-A$1.1m -A$500k-9% on cost · -9% on revenue
Cost stack
  • Construction 500 m² at A$3,700/m²A$1.9m
  • DemolitionA$45k
  • Consultants, DA and certification (9%)A$170k
  • Contributions (A$28,000 per new home)A$28k
  • Contingency (5%)A$100k
  • Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$2.8m instead leaves -A$500k pre-tax on a total development cost of A$5.5m.
TerracesLow and Mid-Rise · FSR 0.9:1 · 12 m 32500 m² A$6.0mA$2.5mA$1.4m-A$1.4m -A$275k-5% on cost · -5% on revenue
Cost stack
  • Construction 500 m² at A$4,300/m²A$2.1m
  • Basement parkingA$100k
  • DemolitionA$45k
  • Consultants, DA and certification (9%)A$200k
  • Contributions (A$28,000 per new home)A$55k
  • Contingency (5%)A$120k
  • Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$2.8m instead leaves -A$275k pre-tax on a total development cost of A$6.0m.

Site facts

Site area
About 800 m² (18 m by 45 m)
Street frontage
About 18 m (measured against the road corridor)
Zone
R3 Medium Density Residential · Randwick Local Environmental Plan 2012
LEP controls
FSR 0.9:1 · height 12 m · minimum lot not mapped
Nearest nominated centre
About 600 m to Kingsford Juniors light rail station (straight line) · 400 to 800 m from a nominated centre
Land value
About A$2,300,000 at 1 July 2025, NSW Valuer General · from A$2,000,000 at 1 July 2021 (+15%)

Neighbours

2 adjoining houses share a boundary with this site. Members see them.