1 house today → about 55 homes as shop-top housing, up to 9 storeys. About 1,000 m², 90 m frontage, zone E2.

Residual land valueA$24.0m
Likely ask (1 house)A$7.0mSuburb median formula (no land value on file)
HeadroomA$17.0m
Claim this site

A$387 inc GST · 3 months

A claim takes this site off the market for every other member for 3 months and opens its address, lot outline, exact figures and neighbours to you.

This site is A$387 because its best option clears a 40% margin on cost at the likely ask. Other sites are A$182. One claim credit claims any site.

Card payment through Stripe. Have an account? Sign in. A claim is exclusive on Build Design Solutions only: it gives no right over the property, and the owner can still sell to anyone. How claims work.

Every option the rules allow

OptionHomesStoreysGFARealisationCostsResidual land valueHeadroomProfit at likely ask
Shop-top housing, up to 9 storeysLow and Mid-Rise (within 400 m) · FSR 6:1 · 32 m 5596,000 m² A$95.0mA$42.5mA$24.0mA$17.0m A$30.0m57% on cost · 32% on revenue
Cost stack
  • Construction 6,000 m² at A$5,600/m²A$35.0m
  • Basement parkingA$1.9m
  • DemolitionA$45k
  • Consultants, DA and certification (9%)A$3.3m
  • Contributions (A$28,000 per new home)A$1.5m
  • Contingency (5%)A$2.0m
  • Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$7.0m instead leaves A$30.0m pre-tax on a total development cost of A$55.0m.
Apartments, up to 9 storeys (LEP controls)Local Environmental Plan · FSR 6:1 · 32 m 5095,000 m² A$85.0mA$35.0mA$23.0mA$16.0m A$30.0m65% on cost · 35% on revenue
Cost stack
  • Construction 5,000 m² at A$5,500/m²A$27.5m
  • Basement parkingA$1.7m
  • DemolitionA$45k
  • Consultants, DA and certification (9%)A$2.8m
  • Contributions (A$28,000 per new home)A$1.4m
  • Contingency (5%)A$1.6m
  • Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$7.0m instead leaves A$30.0m pre-tax on a total development cost of A$45.0m.

Site facts

Site area
About 1,000 m² (25 m by 40 m)
Street frontage
About 90 m (measured against the road corridor)
Zone
E2 Commercial Centre · Waverley Local Environmental Plan 2012
LEP controls
FSR 6:1 · height 32 m · minimum lot not mapped
Nearest nominated centre
About 50 m to Bondi Junction station and town centre (straight line) · Within 400 m of a nominated centre
Notes
DA on record.
Latest DA
A development application is on record for this site. The member who claims it sees the application.