| TownhousesLow and Mid-Rise · FSR 2:1 · 23 m |
8 | 2 | 1,250 m² |
A$15.0m | A$6.0m | A$4.0m | A$1.3m |
A$3.8m40% on cost · 26% on revenue |
Cost stack
- Construction 1,250 m² at A$4,100/m²A$5.0m
- DemolitionA$45k
- Consultants, DA and certification (9%)A$475k
- Contributions (A$28,000 per new home)A$200k
- Contingency (5%)A$275k
- Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$2.8m instead leaves A$3.8m pre-tax on a total development cost of A$9.5m.
|
| Apartments, up to 8 storeys + affordable housing bonusLow and Mid-Rise + Chapter 2 bonus (15% affordable) · FSR 2.6:1 · 29.9 m |
15 | 8 | 1,750 m² |
A$21.0m | A$11.0m | A$3.0m | A$250k |
A$3.8m25% on cost · 18% on revenue |
Cost stack
- Construction 1,750 m² at A$5,500/m²A$9.0m
- Basement parkingA$550k
- DemolitionA$45k
- Consultants, DA and certification (9%)A$850k
- Contributions (A$28,000 per new home)A$425k
- Contingency (5%)A$500k
- Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$2.8m instead leaves A$3.8m pre-tax on a total development cost of A$15.0m. Includes 15% affordable housing at 65% of market.
|
| Apartments, up to 6 storeysLow and Mid-Rise (400 to 800 m) · FSR 2:1 · 23 m |
10 | 6 | 1,250 m² |
A$17.0m | A$9.0m | A$3.0m | A$250k |
A$2.4m19% on cost · 14% on revenue |
Cost stack
- Construction 1,250 m² at A$5,500/m²A$7.0m
- Basement parkingA$400k
- DemolitionA$45k
- Consultants, DA and certification (9%)A$650k
- Contributions (A$28,000 per new home)A$300k
- Contingency (5%)A$400k
- Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$2.8m instead leaves A$2.4m pre-tax on a total development cost of A$13.0m.
|
| TerracesLow and Mid-Rise · FSR 2:1 · 23 m |
4 | 2 | 600 m² |
A$8.0m | A$3.5m | A$2.1m | -A$650k |
A$400k6% on cost · 5% on revenue |
Cost stack
- Construction 600 m² at A$4,300/m²A$2.8m
- Basement parkingA$140k
- DemolitionA$45k
- Consultants, DA and certification (9%)A$250k
- Contributions (A$28,000 per new home)A$85k
- Contingency (5%)A$160k
- Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$2.8m instead leaves A$400k pre-tax on a total development cost of A$7.0m.
|
| Dual occupancyLow and Mid-Rise · FSR 2:1 · 23 m |
2 | 2 | 500 m² |
A$6.0m | A$2.3m | A$1.9m | -A$850k |
-A$65k-1% on cost · -1% on revenue |
Cost stack
- Construction 500 m² at A$3,700/m²A$1.9m
- DemolitionA$45k
- Consultants, DA and certification (9%)A$170k
- Contributions (A$28,000 per new home)A$28k
- Contingency (5%)A$100k
- Then selling costs 3%, GST on the margin, finance 7.5%, stamp duty 5.5% and a 20% developer margin solve for the land. Buying at the likely ask of A$2.8m instead leaves -A$65k pre-tax on a total development cost of A$5.5m.
|